Hello,
I was wondering if anyone has experience the following...
We had a Project set up in AX Dyanmics which incurred a lot of cost in error due to a PO set up. We had to transfer the costs from the wrong project to the correct project. We transferred the cost by doing the following:
-Using the Adjustment transaction for current month items
-Using a $0 AP invoice for older items through Subcontractor and Materials
-Using a $0 Hrs Journal for Labor
Now the old/wrong job has the correct total of Posted Project Transactions (PPT) associated with it. The problem is that when we create the Estimates the Total Cost of the wrong project is not correct and does not tie to the PPT. It shows that we transferred too much to the correct project resulting in a negative total cost.
We unfortunately do not have anyone on our team who has experienced this or knows how to resolve. Is there maybe a hold up in the backend of the system that we just need to clear a cache or is there a report we can run that might show the detail of the Estimates Total Cost?