Master Planning and pegging planned orders

(0) ShareShare
ReportReport
Posted on by

Help please!

Trying to understand if the "Refesh peg.cols" action is a required step when firming planned orders, as we would like to automate firming for transfer orders.

pastedimage1562024160414v1.png

*This post is locked for comments

I have the same question (0)
  • Verified answer
    André Arnaud de Calavon Profile Picture
    305,150 Super User 2026 Season 1 on at

    Hi Mike,

    I have't seen this option before. Can you check if it is a customization or part of a partner solution?

  • Community Member Profile Picture
    on at

    You are correct in that this is a customisation.

    Hence why I cannot find much documentation on it.

  • Suggested answer
    guk1964 Profile Picture
    10,888 on at

    in standard Ax you can autofirm within a time fence.

    In principle when you autofirm then everything is in sync as far as mrp knows - however, that assumes you will not need to action messages, and that there are  not things that mrp does not; know about .e,g. that you plan to  expedite a favoured customer's order, work overtime,  or sub contract, or that you can part ship or that LT can be influenced, or you want o run  to mamimum available material, ..... 

    Whether you should depends on many factors, that will constantly vary e.g.do you make to stock or to order, hw far ahead  you need to firm,   how accurate stable is your forecast, do you use atp/CATP, do you finite or infinite, hw much spare capacity/material do you typically hold, what is the trade off between service and efficient operations - do you lead times and fences reflect that , how long is your production cycle, hw disruptive are changeovers etc. i.e. would you normally always firm without making changes. 

    So its really a how long is apiece of string?, and the answer will vary product by product and maybe period by period, and I suspect  you have already decided that auto firming will work best for your situation. ideally 80% of your business (regular runners, own brand make to stock, long term contracts etc) you should be able to trust to mrp which should be parameterized to optimise cost and service i.e. revenue - . the rest is where decisions are needed and the overall cost- profit makes the extra admin and expediting cost  worthwhile.o

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the April Top 10 Community Leaders

These are the community rock stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
CP04-islander Profile Picture

CP04-islander 24

#2
Michel ROY Profile Picture

Michel ROY 14

#3
Jagadabi Profile Picture

Jagadabi 6

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans