Is there any way in AX 4.0 to set time after the product is complete to ship to an offsite warehouse and have planning consider this?Example: I need to have product arrive in Spain in January (specific sku's). The transit time is 45 days. I need AX to show needing the raw material, capacity and the 45 day carrying cost of the product to complete production mid November. I have been able to get the planned production order to show starting early by updating the coverage group and the reorder safety margin, but when I look at the capacity and material they show as being needed 45 days later.
Can someone help with the setting for this or at least where I could do more testing? Thank
*This post is locked for comments
I have the same question (0)