In Job Card. Job Type -Capital WIP

(0) ShareShare
ReportReport
Posted on by

Hello Experts,

"WIP method must only be Completed Contract in Job No.=00001 with Job Type= Capital WIP."

Why is it so?

Regards,

JO

*This post is locked for comments

I have the same question (0)
  • Saurabh Shah Profile Picture
    4,560 on at

    Hi Jiju,

    Please let me know on which event it is giving you this message.

    For your reference go through below link. you might get your answer.

    msdn.microsoft.com/.../hh172398(v=nav.71).aspx

    plataan.typepad.com/.../confused-by-wip.html

    If you still have any confusion, please ask. :)

    Regards,

    Saurabh Shah

  • Community Member Profile Picture
    on at

    Hi Saurabh,

    Thanks for the reply..

    I just need to know the reason behind the "WIP method must only be Completed Contract in Job No.=00001 with Job Type= Capital WIP."

  • Community Member Profile Picture
    on at

    Let me clarify my question,

    The sysetm doesn't allow any Job other than Completed Job with  Job type with "Capital WIP"

    I just want to know why. See the picture:

  • Verified answer
    Community Member Profile Picture
    on at

    If an asset is not completed at that time when balance sheet is prepared, all costs incurred on that asset up tot he balance sheet date are transferred to an account called Capital Work in Progress Account.

    This account is shown separately in the balance sheet below the fixed asset.

    Capital work in progress account contains all expenses incurred on the asset until it is converted into working condition. All these expenseswill become part of the cost of that asset

    www.zeepedia.com/read.php;b=23&c=20

    What I understood is as follows:

    Capital work in progress account contains all expenses incurred on the asset until it is converted into working condition. (That is on Completion). All these expenseswill become part of the cost of that asset.

    That is why the Posting will be done only on completion of asset.

    So that's why the system is not allowing in this case...

    If anyone wants to share their opinion, please do

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics NAV (Archived)

#1
HoangNam Profile Picture

HoangNam 7

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans