Hi,
Do you know if the Realized cost amount field for BOM lines on the Price calculation form (Production order > View > Price calculation) calculates the amount based on the item's cost or realized cost from BOM's production order?
Thank you
Hi,
Do you know if the Realized cost amount field for BOM lines on the Price calculation form (Production order > View > Price calculation) calculates the amount based on the item's cost or realized cost from BOM's production order?
Thank you
Just to confirm. If a BOM was posted to inventory from a production order, then it's realized cost from that production order will be used for the Realized cost calculation, when it's pulled into another production orders picking list. Is that correct?
Hi silentsquirrel,
I would say both :-)
There should be an estimated and realized cost column available.
The first one is calculated, the second one based on the realized costs.
Best regards,
Ludwig