Projects (job) and manufacturing

(5) ShareShare
ReportReport
Posted on by 112
 

Hi everyone,

 

 

 

I’d like to understand if MRP and MPS are fully integrated with the project module. Specifically, if you add a production-type item (with BOM and routing, not assembly) to the project planning lines, will this item be recognized by MPS and MRP in the new version?

 

 

 

Your insights would be greatly appreciated!

I have the same question (0)
  • Suggested answer
    YUN ZHU Profile Picture
    99,086 Super User 2026 Season 1 on at
    As far as I know, no.

    Hopefully other experts can give you better advice.
     
    Thanks.
    ZHU
  • Verified answer
    Jainam M. Kothari Profile Picture
    15,803 Super User 2026 Season 1 on at
    Hello,
     
    Yes, in the latest version of Business Central, MRP (Material Requirements Planning) and MPS (Master Production Scheduling) are fully integrated with the project module. When you add a production-type item (with BOM and routing) to the project planning lines, this item will be recognized by both MPS and MRP
     
    This integration ensures that the planning system can calculate the necessary production schedules and material requirements based on the demand from the project planning lines. This helps in maintaining accurate and efficient planning for production and material needs.
     
     
     
  • Gerardo Rentería García Profile Picture
    25,555 Most Valuable Professional on at

    Hi, good day
    I hope this can help you, and give you some hints.

    Assemble to Project - Business Central | Microsoft Learn

    Best Regards
    Gerardo

  • Verified answer
    Ben Baxter Profile Picture
    6,918 Super User 2026 Season 1 on at
    The answer is yes.  You need to ensure the Project has Apply Usage Link enabled, the Project is in Open status, and the Planning Date is within your time horizon of the Calc. Plan.  The suggestion should create a Planned Production Order suggestion and calculate any needs for the related BOM.
     
    Best Regards,
    Ben Baxter
    Accent Software Inc
  • Ramesh Kumar Profile Picture
    7,547 Super User 2026 Season 1 on at
    Short answer is yes
     
     
    Thanks
    Ramesh
     
    If this was helpful, please check the "Does this answer your question?" box and mark it as verified.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 2,005 Super User 2026 Season 1

#2
YUN ZHU Profile Picture

YUN ZHU 1,148 Super User 2026 Season 1

#3
Khushbu Rajvi. Profile Picture

Khushbu Rajvi. 557 Super User 2026 Season 1

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans