Announcements
HI
I'm cannot cancel or correct a Project PO Receipt, The system warns that Cannot cancel the product receipt ##### as it has linked item requirements.
Hi BMicrosoftDynamcis365,
Right.
Has your issue been resolved by posting the negative quantity or is there still something that needs to be fixed?
Best regards,
Ludwig
Thank you
But on-hand Inventory Increase when post a negative quantity of the item
Hello BMicrosoftDynamicsD365,
You can create a new PO line with a negative quantity and post this one to the project in the same way as you posted the original one.
An easier and faster alternative is creating a new item requirement or project item journal and post a negative quantity of the item used.
This should have the same effect.
Best regards,
Ludwig