Hi community,
I'm facing this issue and i don't understand why i get the warning message.
Here is the context:
I'm on version 10.0.25 (PU49).
I have multiple Legal Entities and need intercompany order between them.
When i create a Purchase Order in the company B, it creates a Sales Order in company A. And when i add an item to the line, i get this message :
Company : A The entered ship date dd/mm/yyyy is not valid because it is within the sales lead time period.
dd/mm/yyyy = today.
However, on company A changing the sales lead time (0n 10 days, 30 days...) doesn't matter. I still have the same warning message on the PO in company B.
Second point : if i change the delivery date on the header on my PO, it changes the Requested Ship Date on the Intercompany SO (what i beleive is refered is the warning message as "enetered ship date"), but even if the date i far in the future (and not in the lead time), i have the same message.
Does anyone