Fixed Asset Number field in Project management is Disabled

Posted on by 14,849

Dear 

I am trying to connect a fixed asset to a certain project (of type Investment), but the fixed asset number field in the project Setup tab is disabled, how can i open it ? 

am i missing anything in the setup ?

Regards

*This post is locked for comments

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Fixed Asset Number field in Project management is Disabled

    Hey Patrick,

    Maybe this Information helps: dynamicsax-fico.com/.../construction-in-progress-project-module

    Ludwig

  • Verified answer
    David Massey Profile Picture
    David Massey on at
    RE: Fixed Asset Number field in Project management is Disabled

    When running the elimination, set eliminate to Fixed Asset. Specify the Asset Id and Valuation model.  (General tab)

  • Abdo Khoury Profile Picture
    Abdo Khoury 14,849 on at
    RE: Fixed Asset Number field in Project management is Disabled

    Hey Ludwig

    i have already created a project and an estimate and i have posted actual cost to that project and i am now at the stage where i will press "Eliminate" but the fixed asset field is still disabled,

    what am i missing ?

  • Verified answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Fixed Asset Number field in Project management is Disabled

    Hello Patrick, Before you eliminate the project you manually select the fixed asset to which you plan to transfer all cost. Once the elimination is posted, AX automatically has the link to your fixed asset and can display the fixed asset linked to your project. Hope it helps, Ludwig

  • Abdo Khoury Profile Picture
    Abdo Khoury 14,849 on at
    RE: Fixed Asset Number field in Project management is Disabled

    so if i understand correct, there is no way for me to link the Fixed asset to the project since this estimate project id field will be auto populated at the creation of the Project ....

    so how do i link a fixed asset to a project

  • Suggested answer
    David Massey Profile Picture
    David Massey on at
    RE: Fixed Asset Number field in Project management is Disabled

    The fixed asset field is enabled if there is no estimate project id specified for Investment, Internal or cost project types and the project status is not finished.  Once the estimate project id field contains a value the fixed asset field is disabled.  By default the project estimate id field is auto populated during the creation of the project.

    No project functionality uses this field as it is reference only.

  • Verified answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Fixed Asset Number field in Project management is Disabled

    Hello Patrick, the fixed asset field that you can identify in the Projects form cannot directly be edited. What you need to do first is run an estimate and eliminate the project to a fixed asset. You can either search TechNet on how this process works or wait until the end of this week as I will post the steps required on my blog. All the best, Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Community AMA December 12th

Join us as we continue to demystify the Dynamics 365 Contact Center

New! Quick response templatesâš¡

Save time with the new custom templates!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,228 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,056 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans