PROJECT REVENUE RECOGNITION

(0) ShareShare
ReportReport
Posted on by 63

Hi,

We have around 100 Projects which we use percentage of Completion as a Revenue Recognition Method,

Can I book the Accrued Revenue for all Projects ONE TIME  NOT ONE BY ONE

Note;

All those Projects are Under One Project Group  

Thanks & Regards

Mustafa

I have the same question (0)
  • Verified answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Mustafa,

    There is a periodic function available that allows you posting the project estimates for multiple projects at once.

    Please search for it in your menu structure in the project module.

    Once you found it you can post the accrued revenue for all of the 100 projects without having to open them one by one.

    Best regards,

    Ludwig

  • Mustafa Quraitem Profile Picture
    63 on at

    Hi Ludwig,

    Can you please let me know what this periodic function is?

    Regards

    Mustafa

  • Verified answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Good Morning Mustafa,

    In D365FO you can find the functionalities under project management / Periodic / Estimates.

    There you can create, calculate, post ... estimates for multiple projects.

    Best regards,

    Ludwig

  • Mustafa Quraitem Profile Picture
    63 on at

    Hi Ludwig,

    As per me, For posting the project estimates for multiple projects at once,  The estimated Cost should be defined for each Project in its Profile , Am I Right ?

    Regards

    Mustafa

  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Mustafa,

    I don't understand your last question.

    Can you clarify it and possibly provide an example or screenshot?

    Many thanks,

    Ludwig

  • Mustafa Quraitem Profile Picture
    63 on at

    Hi Ludwig,

    Actually my inquiry is about (Percentage complete) thru Revenue Recognition, In setup there are many Calculation Options (Manual Or Cost,..) , My Question is if I selected (Cost).. WHAT IS the Equation?? Actual Cost will be divided by which figure ?

    Thanks & Regards

    Mustafa

  • Verified answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hello Mustafa,

    The actual costs are compared against the forecast costs that you selected when running the estimate (remember that you must select a forecast model). What AX calculates and how it calculates depends on the calculation method selected. The following blog post provides an overview of the available methods.

    docs.microsoft.com/.../estimate-calculation-methods-for-fixed-price-projects

    Best regards,

    Ludwig

  • Suggested answer
    Gaurangkumar Jani Profile Picture
    4,534 User Group Leader on at

    Hi Mustafa,

    Are you asking for following setup:

    pastedimage1578968548370v2.png

    There are three option:

    1. Manual which will allow you to enter Percentage completion manually.

    2. Automatic which will calculate percentage completion by calculating all actual cost against estimated cost.

    3. Cost Template which will allow you to calculate percentage completion as per cost template selected in Project group.

    Following are example of cost template where I mention completion method is automatic.

    pastedimage1578968848040v3.png

    Let me know if this solve this issue.

    For booking multiple revenue without going to each project, as Ludwig Reinhard suggested best way to do it.

    Following are the options you can use it for bulk creation / deletion / posting as well as for reversal.

    pastedimage1578969028953v4.png

    For more information regarding Fixed Price Contract with Percentage completion method you can refer following blog:

    https://dynamics365finance.wordpress.com/2019/06/03/fixed-price-percentage-completion-contract-with-milestone-billing-full-cycle/

    Let me know if any more help required.

    Thanks,

    Gaurangkumar Jani

    D365 Finance Functional Consultant

  • Mustafa Quraitem Profile Picture
    63 on at

    Hi Jani,

    Thanks for your detailed response, Currently All is Ok with me EXCEPT One Point ( Where can I mention The Estimated Cost for a Particular Project?)

    Regards

    Mustafa  

  • Verified answer
    Gaurangkumar Jani Profile Picture
    4,534 User Group Leader on at

    In project forecast.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 467 Super User 2025 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 420 Most Valuable Professional

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 241 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans