Change Category group assigned to Project category

Posted on by Microsoft Employee

We started out implementing AX2012 Project management and accounting at one of our business units, and by the second realized that we had too many Category groups and streamlined them for the remaining 14 business units. We'd like to now maintain the Category group on the Project categories in the first BU to match the rest to make global reporting easier. Is there a front end method of doing this? When I look at the Project categories, the field for Category group is greyed out and I see no Function or option to maintain it.

  • Community Member Profile Picture
    Community Member Microsoft Employee on at
    RE: Change Category group assigned to Project category

    Thanks Ludwig - that's what I thought.

  • Verified answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Change Category group assigned to Project category

    Hi,

    this is right.

    when you setup categories you have to associate them to a category group that cannot be changed later on.

    the best option is creating new categories especially if you used the v existing  ones for postings already.

    best regards

    ludwig

Helpful resources

Quick Links

Dynamics 365 Community Update

Welcome to the inaugural Community Platform Update. As part of our commitment to…

Dynamics 365 Community Newsletter - August 2024

Catch up on the latest D365 Community news

Community Spotlight of the Month

Kudos to Mohana Yadav!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 290,142 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 227,979 Super User 2024 Season 2

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans