Requirement date for Planning optimization

(0) ShareShare
ReportReport
Posted on by 15

Hi, 

does the planning optimization calculate the requirement date as TODAY'S + LEAD TIME in every case? 

In the example below, the purchase lead time is 2 days. 

I expected the planned order covering the sales order to have the requirement date = 05/29. 

So the planning optimization in every case always considers the requirement date as today + lead time? 

pastedimage1679431812975v1.png

Thanks

I have the same question (0)
  • Suggested answer
    Charlotte X Profile Picture
    Microsoft Employee on at

    Hi Pierluigi,

    It depends on the scenario. Please refer to this article:

    D365 Master Planning Dates - Requested vs Requirement Dates (sikich.com)

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Launch!

Jump in, show your community spirit, and win prizes!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the April Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 145 Super User 2026 Season 1

#2
Abhilash Warrier Profile Picture

Abhilash Warrier 102 Super User 2026 Season 1

#3
Laurens vd Tang Profile Picture

Laurens vd Tang 97 Super User 2026 Season 1

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans