I have a simple T&M project setup whereby we procure services using procurement categories and we mark them up by 10% when we issue them to the project. We do that using a sales price group and a charges percent mark up.
Some purchase order lines do not follow that rule. Since they are few and far in between, we ask the users to override the sales price on the PO line before the PO is approved and confirmed.
The result is that the PO will show the correct value on the pending transactions screen after product receipt. However, when the PO invoice is posted, the system applies the 10% mark up again.
Default the project sales price from purchase line during PO vendor invoice.
Was this reply helpful?YesNo
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.