Hello Projects People!
I'm configuring Vendor retention on Projects in F&O. I configured a simple vendor retention group and applied on a PO. Works well but I noticed that the retained amount is not on the ProjTrans record and is therefore not WIP or accrued revenue...am I missing some config or is this by design?
For example, I have a 10% retention, there's a $10000 PO which is "fully" invoiced. I see the $9000 VendTrans and ProjTrans (and therefore WIP/accrued revenue) and $1000 to the GL account I specified for Vendor retention in Automatic transactions in the GL. The full $10000 should be costed on the ProjTrans record so that the Project customer can be billed the full value, not just $9000.
Am I missing anything?
Thanks in advance.
Aaron