Hi,
we are facing at our customer the following challenge in production scheduling:
ProdRoute line Primary: ressource (=machine) has a 24h calendar
line Secondary-1: ressource (=worker) has a 8h calendar
In real production the operator fills the machine and leaves the plant in the evening but the machine is still running all night. When scheduling the production order the secondary route determines the lead time. E.g. the work load for the machine is 20 hours (specified in primary line) but the production is scheduled for almost 3 days because the worker has only 8 hours capacity a day (limited capacity in ressource is not set).
Working with load percentage does not help.
Is there any chance to tell AX only to use the primary route line for scheduling?