Creating a "wait" period inside route operation in AX 2012

(0) ShareShare
ReportReport
Posted on by 10

Our company is introducing a new product. Production flow is as following

Operation 1

Wait period of 24 hours

Operation 2

I have setup an operation for the wait period however if i create production order for 2 pcs the "wait" period operation is multiplied but the number of units on the production order creating a 48 hour wait period when in reality its only 24 hours from when the operator finished the 1st operation.

For example; if the first piece is processed at 9am, operation 2 can commence at 9am the next day. If the second piece is processed at 9:10am, operation 2 can commence at 9:10 am the next day. 

How do I create a waiting period on the route for the items?

  • Verified answer
    André Arnaud de Calavon Profile Picture
    André Arnaud de Cal... 291,735 Super User 2024 Season 2 on at
    RE: Creating a "wait" period inside route operation in AX 2012

    Hi TK1,

    Have you tried setup the field 'Queue time after' on Operation 1 instead of the 'wait' operation?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Congratulations 2024 Spotlight Honorees

Kudos to all of our 2024 community stars! 🎉

Meet the Top 10 leaders for December

Congratulations to our December super stars! 🥳

Start Your Super User Journey

Join the ranks of our community heros! 🦹

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,735 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,466 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Product updates

Dynamics 365 release plans