Hi I am completely new here and need some help with MRP
I want to setup an MRP to create Purch requisition. What I am looking for is a setup to
1. look 1 yr in the future
2. create the Purch requisition when Stock goes under the safety stock defined (eg. we have a sales order to be delivered in 2 month, the item has a lead time of 6 weeks so the PO should be created the lead time (plus a safety) before it is needed.
Setup a coverage group with Coverage Code Requirement and Coverage time fence 365 Days (Demand for the future year). You can also add a min qty for safety stock and the purchase lead time on the Item master Plan tab - Item Coverage. MRP will create a plan order is you go below safety stock levels with the requirement date Today + Lead time.
you could find the bacis setup for MRP from :
Dynamics 365 Supply Chain Management: The Basics of MRP Tch Talk
Any Idea how to get my results?
yes but my question was how to do te setup to get the mentioned results
1. look 1 yr in the future
2. create the planned Purchase orders when Stock goes under the safety stock defined (eg. we have a sales order to be delivered in 2 month, the item has a lead time of 6 weeks so the PO should be created the lead time (plus a safety) before it is needed.
YES, MRP will only generate planned purchase order and planned production order according to the item set up.
Hi Yes sorry thats what I ment. I misstype while had a phone call during my post about purch requisition. My fault. For sure planned purchase orders.
But the problem stays the same ;-)
Hi MVT75,
The Master planning is not able to create purchase requisitions. It can create planned purchase orders and planned production order.