Hi I am completely new here and need some help with MRP

I want to setup an MRP to create Purch requisition. What I am looking for is a setup to 

1. look 1 yr in the future 

2. create the Purch requisition when Stock goes under the safety stock defined (eg. we have a sales order to be delivered in 2 month, the item has a lead time of 6 weeks so the PO should be created the lead time (plus a safety) before it is needed.

I have the same question (0)
  • André Arnaud de Calavon Profile Picture
    301,035 Super User 2025 Season 2 on at

    Hi MVT75,

    The Master planning is not able to create purchase requisitions. It can create planned purchase orders and planned production order.

  • Community Member Profile Picture
    on at

    Hi Yes sorry thats what I ment. I misstype while had a phone call during my post about purch requisition. My fault. For sure planned purchase orders.

    But the problem stays the same ;-)

  • Microsoft Profile Picture
    on at

    YES, MRP will only generate planned purchase order and planned production order according to the item set up.

  • Community Member Profile Picture
    on at

    yes but my question was how to do te setup to get the mentioned results

    1. look 1 yr in the future

    2. create the planned Purchase orders when Stock goes under the safety stock defined (eg. we have a sales order to be delivered in 2 month, the item has a lead time of 6 weeks so the PO should be created the lead time (plus a safety) before it is needed.

  • Community Member Profile Picture
    on at

    Any Idea how to get my results?

  • Microsoft Profile Picture
    on at

    you could find the bacis setup for MRP from : 

    Dynamics 365 Supply Chain Management: The Basics of MRP Tch Talk

  • Suggested answer
    Sumendree_Pandarum Profile Picture
    15 on at

    Setup a coverage group with Coverage Code Requirement and Coverage time fence 365 Days (Demand for the future year). You can also add a min qty for safety stock and the purchase lead time on the Item master Plan tab - Item Coverage. MRP will create a plan order is you go below safety stock levels with the requirement date Today + Lead time.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 611 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 529 Super User 2025 Season 2

#3
Sohaib Cheema Profile Picture

Sohaib Cheema 285 User Group Leader

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans