Skip to main content

Notifications

Announcements

No record found.

Community site session details

Community site session details

Session Id :
Microsoft Dynamics NAV (Archived)

Production Order refresh

(0) ShareShare
ReportReport
Posted on by 225

One more problem.

I have problem with production order. I made new work center (A) and made new routing with only one line (work center A). A assign this routing to item and I made released production order with this item source. When I start Refresh command, I get message:

Error when calculating backward. Calendar is not available before date for work center A.

*This post is locked for comments

  • bosovik Profile Picture
    225 on at
    RE: Production Order refresh

    Finally. Thanks a lot.

  • Verified answer
    Aleksandar Totovic Profile Picture
    16,765 on at
    RE: Production Order refresh

    Then unmark this field and calculate Work Center Calendar again. This will solve your problems.

    This field tell to NAV that Work Center's availability is equal to the sum of the machine center capacities.

    Considering that, you don't use Machine Centers, then sum is zero.

    This field you need to use only if you use machine centers. But and then, you first check method you want to use for planning.

  • bosovik Profile Picture
    225 on at
    RE: Production Order refresh

    No, I don't use machine centers and yes, this field is marked.

  • Suggested answer
    Aleksandar Totovic Profile Picture
    16,765 on at
    RE: Production Order refresh

    Do you use Machine Centers? If no, tell me what value is in Consolidated Calendar field.

  • bosovik Profile Picture
    225 on at
    RE: Production Order refresh

    There are only zeros. I calculate this WC again and again, and everytime get zeros.

  • Suggested answer
    Aleksandar Totovic Profile Picture
    16,765 on at
    RE: Production Order refresh

    There are truly small quantites. However, look at Work Center Calendar and tell us what values are in this Work Center line.

  • bosovik Profile Picture
    225 on at
    RE: Production Order refresh

    Quantity is 20; Setum time is 45 minutes and Run time is 22 minutes.

    This is small quantity and this is first time I use this WC.

  • Suggested answer
    Aleksandar Totovic Profile Picture
    16,765 on at
    RE: Production Order refresh

    What is Quantity on Production Order? What is Setup Time and Run Time on this item Routing? Do you set any other time on routing?

    Maybe, this quantites and times are problem. Try to calculate quantity and time by hand and compare with avalibility in calendar.

  • bosovik Profile Picture
    225 on at
    RE: Production Order refresh

    I calculated at the same time when I created work center for current year.

  • Suggested answer
    Aleksandar Totovic Profile Picture
    16,765 on at
    RE: Production Order refresh

    Are you calculate Work Center Calendar? I think this is a problem.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

🌸 Community Spring Festival 2025 Challenge Winners! 🌸

Congratulations to all our community participants!

Adis Hodzic – Community Spotlight

We are honored to recognize Adis Hodzic as our May 2025 Community…

Kudos to the April Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard > Microsoft Dynamics NAV (Archived)

Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans