Project Budget Workflow Approval Issue

(0) ShareShare
ReportReport
Posted on by

The below error is generated after the final approval of Project Budget though workflow.

"No account number exists for account type Cost for project *********".

*This post is locked for comments

I have the same question (0)
  • Verified answer
    Bilal Issa Profile Picture
    4,370 on at
    RE: Project Budget Workflow Approval Issue

    Hi,

    please try to setup an account on project management -> setup -> posting -> Ledger posting setup -> cost.

    Regards,

    Bilal

  • Verified answer
    Community Member Profile Picture
    on at
    RE: Project Budget Workflow Approval Issue

    it seems to be setup issue.

    Please review if you have proper setup at following setup form in Project Management and Accounting module

    \Menus\ProjectManagementAndAccounting\Setup\Posting\Ledger posting setup

    Please verify and update us with your finidngs

  • Community Member Profile Picture
    on at
    RE: Project Budget Workflow Approval Issue

    Ledger Posting Setup is already setup.

    Project Budget is already approved and now once the same budget(with the same categories, but amount is made "Plus" "Minus") is Revised with the workflow approval its creating the above issue.

  • Community Member Profile Picture
    on at
    RE: Project Budget Workflow Approval Issue

    @Bilal Issa

    @Nitesh Ranjan

    Sorry for the previous reply, bcoz already setup was done, but few categories were missing.

    Again my doubt here is: at the first time once we posted the budget it was approved for all the categories including the missing categories in Ledger Posting setup.

    Now again we are revising the budget then its generating the error msg.

    So why is this happening. If "account" is not setup for a category then it should generate the error at the first time itself, still why in the revision?

  • Drumboss Profile Picture
    170 on at
    RE: Project Budget Workflow Approval Issue

    Dear Imtyyaz,

    We are experiencing the same. I noticed though that it only happens when the approval/posting is related to submitted TimeSheets that have lines with multiple company projects.

    Perhaps this info could help you. Does it happen to you also only when you have projects with multiple companies?

    Tx, good luck,

    John

     try to approve / post

    No account number exists for account type Cost for project

  • Community Member Profile Picture
    on at
    RE: Project Budget Workflow Approval Issue

    Hi Imtiyaz,

    Verify the Financial dimensions in the Project setup, that they have the correct project.

    Regards,

    Pablo

  • Mohammed Abdul Aziz Profile Picture
    1,875 on at
    RE: Project Budget Workflow Approval Issue

    All,

    Did anyone find a fix for this issue. I am getting same error when posting timesheets for different legal entities.

    No account number exists for account type Cost for project *********

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Priya_K Profile Picture

Priya_K 4

#2
Alexey Lekanov Profile Picture

Alexey Lekanov 3

#3
Scott_itD Profile Picture

Scott_itD 2 Community Manager

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans