Production order No.##### could not be scheduled. Not enough capacity could be found in AX-2012

(0) ShareShare
ReportReport
Posted on by 130

Assalam o alikum

Dear All

"Production order No. ##### could not be scheduled. Not enough capacity could be found in AX-2012."  I am facing this problum on updating production order status to shedule. please help me to resolve this problum.

*This post is locked for comments

I have the same question (0)
  • Verified answer
    Community Member Profile Picture
    on at

    Mohammad,

    Do all the Resource and Resource groups within your route have a calendar within enough horizon? Did you fill in both the process quantity and corresponding process time within your route? Do you use a load percentage < 100% within your route?

  • George Thogo Profile Picture
    15 on at

    This requires changing the production status and production control parameters.

    Untick the job sheduling and operation scheduling if scheduling is not required while starting a production / batch order.

  • Verified answer
    Amit Rawal Profile Picture
    25 on at

    1. Check the routing for each operation. Your operation time is exceeding the calendar horizon.

  • Mohammad Waseem Profile Picture
    130 on at

    Thankx to all for there support and cooperation.

  • Suggested answer
    Weaveriski Profile Picture
    23,618 Moderator on at

    A question asked so many times that the Manufacturing R&D team wrote a blog on it :-)

    blogs.msdn.com/.../production-order-could-not-be-scheduled-not-enough-capacity-could-be-found-how-to-get-to-the-bottom-of-this.aspx

  • sekhark Profile Picture
    86 on at

    Hi Steven Weaver,

    This page has been disabled. Can you please provide any other link or blog.

  • Eric Fresneau Profile Picture
    45 on at

    Hi,

    This page has been disabled but we always have the same question ;-). Can you please provide any other link or blog ? Many thanks

  • gmazzetto1 Profile Picture
    13 on at

    Mohamad,

    I have found that for some reason when the route has capability instead of resource/resource group assigned to the operations, scheduling the production/batch order by operation the error comes up. In the other hand, scheduling it by job it works fine.

    Maybe the scheduling logic isn't able to identify resources when capability is assigned. Which makes sense, since operation scheduling can't reach the resource's capability.

  • Suggested answer
    D365 Talent Profile Picture
    25 on at

    Hello Mohammad,

    Please check below things for the issue.

    1) Open calendar and check working time & extend it bit longer.

    2) One temporary solution:-  For the temporary solution we can restrict to system to check resource capacity load. We can untick finite capacity under the resource so that system will not check capacity validation and schedule the planned production order.

    Update master planning for the specific item/Whole after performing 2nd step as mentioned above.

    Thanks 

    Yash

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans