Project invoicing - How to process three stage invoices?

(0) ShareShare
ReportReport
Posted on by 251

Hi All,

I am wondering how to process following scenario in D365 F&O Project module?

Budgeted contract value of the project is £10000 and I would like to be able to generate invoice proposals via the billing rule once following milestones have been hit. 

Milestone 1 - With Order (Advance) Payment - 30% of the contract value

Milestone 2 - Prior to Dispatch Payment - 60% of the contract value

Milestone 3 - 30 days net after dispatch of the item requirement on the project. - Remaining 10% of the contract value.

I tried the milestone type billing rule, however I have to manually calculate the values instead of system calculating % of the contract value.

Is it possible to do this in both T&M and Fixed Price project?

Thanks,

Amit

I have the same question (0)
  • Verified answer
    André Arnaud de Calavon Profile Picture
    301,075 Super User 2025 Season 2 on at

    Hi Amit,

    Out of the box, managing invoices based on milestones is for this scenario cumbersome. The values have to be calculated in most cases manually. In the past, we had customized the process of creating billing rules or on-account transactions to get more automation.

  • Amitsb1980 Profile Picture
    251 on at

    Hi Andre, Thanks. I thought it to be the case.

    I have raised an idea with MS to see if the milestone billing rule can have functionality to calculate % of the contract value. It has this functionality for fee type billing rule but not extended elsewhere.

    experience.dynamics.com/.../

    I would appreciate your vote for it.

    Thanks,

    Amit

  • Suggested answer
    Junaid Idrees Profile Picture
    on at

    Hi Amit Bhawalkar,

    Unfortunately we cannot create billing rules with Milestone %, you have to calculate the sales price manually and specify for respective Milestone and system will calculate total contract value automatically.

    I voted :)

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Amit,

    What about progress based billing rules?

    Can they fit your scenario?

    docs.microsoft.com/.../create-a-project-contract-to-invoice-for-progress-billings

    Best regards,

    Ludwig

  • Amitsb1980 Profile Picture
    251 on at

    Hi Ludwig,

    Thanks, I will explore the progress based billing rule further.

    As we are an engineering company, typically we will not invoice the customer for by time (hrs) but mainly by material (finished manufactured product). I could potentially set-up project categories such as Design, Dispatch etc. and set-up billing rule to look at these categories and calculate % of the total contract price as the invoice.

    I will try this out on my environment and report back.

    Regards,

    Amit

  • Amitsb1980 Profile Picture
    251 on at

    Hi Ludwig,

    Tried using the progress billing option. Unfortunately, it still doesn't give me the option to provide Fee %. It seems, I will still have to manually calculate values and add them to the contract value field which really doesn't help my case.

    pastedimage1605611011854v1.png

    I really think, Microsoft needs to bring in this simple functionality to make the billing rule more intuitive. Below is the link to the idea post, I had created. It would be great to have your vote.

    experience.dynamics.com/.../

    Thanks,

    Amit

  • Verified answer
    Amitsb1980 Profile Picture
    251 on at

    Having played around, I managed to find following workaround which doesn't involve billing rule.

    1. Create or import revenue budget.

    2. Create customer advance as % of revenue budget. Here, I create my stage 1 invoice proposal by specifying 30% of the contract value.

    3. Post this to create on-account transaction on the project.

    4. Create another customer advance request as % of the revenue of the budget nearer to the completion of the project to create the 60% prior to dispatch payment.

    5. Post this to create 2nd on-account transaction.

    6. Once a delivery note for the item requirement on this project is posted, one can create a stage 3 invoice which will be for the total contract value, however the invoice will show the two on-account deductions, making it only 10% of the contract value payable.

    I still think, having the ability to use milestone billing rule to create these invoice automatically is the best way forward. Only if MS can allow % to be specified on the billing rule.

    Hope this helps someone in similar shoes.

    Thanks,

    Amit

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 551 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 450 Super User 2025 Season 2

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 278 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans