Description: We are facing a scenario where budget control is enabled across the full procurement process — from Purchase Requisition (PR) to Vendor Invoice.
In one particular case, a PR exceeded the available budget. A budget approval request was submitted and subsequently approved. Then, additional budget was allocated, and the PR was successfully approved.
However, after a significant delay, when converting this PR into a Purchase Order (PO), we encountered a new budget control blockage.
Question: How can we allocate and reserve budget at the PR level and have that same budget commitment carried forward to the related PO, in order to avoid repeated budget blockages for the same transaction?
Any best practices or setup recommendations to maintain the initial budget commitment from PR to PO would be appreciated.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our 2026 Super Stars!
We are thrilled to have these Champions in our Community!
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Giorgio Bonacorsi 658
André Arnaud de Cal... 468 Super User 2026 Season 1
Syed Haris Shah 333 Super User 2026 Season 1