Ability to Build BOMs from the bottom up

(0) ShareShare
ReportReport
Posted on by

We have BOMs that have multiple sub assemblies.

- When we go to Build the top level BOM we are often stopped because one of the sub assembly BOMs have not been completed.  So we are faced with:

- come out to build the sub assembly BOM

- go back into the Top Level BOM and try building it again. 

- We may be faced yet again with another sub assembly that was not built and have to repeat the above steps.

Previous software we have worked with would build the BOM from the bottom up.  Is there a feature or process that would enable us to do this?

Many thanks!

*This post is locked for comments

I have the same question (0)
  • Hannes Holst Profile Picture
    5,767 on at

    Hi,

    I'm guessing the problem is because of missing inventory?

    In that situation you have several options.

    You could run one of the Inventory Reports to check that you sufficient inventory. As alternative, in Assembly Orders you can see the Availability of each Item in the FactBox on right.

    Or, in an Assembly Order you could execute "Explode BOM". Then the underlaying BOM would be inserted into the current Assembly Order. Instead of e.g. 3 Assembly Orders, you would have to manage one Assembly Order only. But in this situation, you cannot amend the Quantity of the underlaying BOMs (you can only assembly as much as for the current Assembly Order is needed).

  • Community Member Profile Picture
    on at

    Thank you for your feedback.  It isn't so much as having missing inventory rather that in the multi level BOM the top level (Parent) is being built with the ASSUMPTION that all underlying BOMs have already been built.  This is not necessarily the case and therefore when the top level BOM is being built, there are instances where one of the underlying BOMs  have not been built so we have to come out, build the underlying BOM that was not showing as being available, then go back in and try again.  This could happen a number of times since there are many sub assy's in our BOMs.  It is possible that we are missing something (minimal training was provided and essentially going by what we know).

    Thanks for your input and feedback!

  • Hannes Holst Profile Picture
    5,767 on at

    Hi,

    Here you'll find detailed information about Assembly Orders/BOMs in NAV:

    docs.microsoft.com/.../assembly-assemble-items

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics NAV (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans