Reopening a Cancelled PO Line

Posted on by Microsoft Employee

Hello,

A PO line got cancelled by mistake and caused the whole PO to become invoiced. We need to reopen the line, but can't since it is now fully invoiced. We have tried looking into opening it through tables, but have had no success.

Any and all help would be greatly appreciated.

*This post is locked for comments

  • Community Member Profile Picture
    Community Member Microsoft Employee on at
    RE: Reopening a Cancelled PO Line

    AX 2009

  • Community Member Profile Picture
    Community Member Microsoft Employee on at
    RE: Reopening a Cancelled PO Line

    Thanks, that was it. After discussion, we realized that could have potentially done a separate invoice, and tied it in with the PO later. But there is always the risk of not being able to.

  • Verified answer
    André Arnaud de Calavon Profile Picture
    André Arnaud de Cal... 291,113 Super User 2024 Season 2 on at
    RE: Reopening a Cancelled PO Line

    Hi,

    The field on the PurchTable is set to invisible. So in AX you will not see the contents. You can see it in the SQL management studio.

    As the field on the Purchase line is not activated, you should be able to change the deliver remainder (Purchase order details, select the line and click, Update Line, Delivery remainder.)

    Also check the purhcase parameter 'Safety level of invoiced orders'. This should not have the value 'Locked' when you want to reopen the order.

    When changing the deliver remainder you set the quantity you will still receive.

    Please update this thread with your findings.

  • Community Member Profile Picture
    Community Member Microsoft Employee on at
    RE: Reopening a Cancelled PO Line

    Thanks Andre.

    Looking into the Tables, the IsFinalized field appears to be inactive. Also, the FinalizeClosingDate field is not there. Was this field added in CU6 or CU7?

  • Suggested answer
    André Arnaud de Calavon Profile Picture
    André Arnaud de Cal... 291,113 Super User 2024 Season 2 on at
    RE: Reopening a Cancelled PO Line

    Hi,

    In this version there is a field called IsFinalized on the PurchLine which prevents all new updates on the purchase order once it has the value 'true''. Also the purchase parameter for safety level is ignored then.

    I have wondered why this field was introduced in AX2012, but never disabled it before to do new updates. If you do it yourself, first check possible consequences in another environment.

    Note that also a field exists on the PurchTable called FinalizeClosingDate. Maybe this field is related to this Finalizing state as well.

  • Community Member Profile Picture
    Community Member Microsoft Employee on at
    RE: Reopening a Cancelled PO Line

    AX 2012 R2

  • André Arnaud de Calavon Profile Picture
    André Arnaud de Cal... 291,113 Super User 2024 Season 2 on at
    RE: Reopening a Cancelled PO Line

    Hi,

    Can you tell us what version of AX you are using?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

November Spotlight Star - Khushbu Rajvi

Congratulations to a top community star!

Forum Structure Changes Complete!

🔔 Be sure to subscribe to the new forums you are interested in to stay up to date! 🔔

Dynamics 365 Community Platform update – Oct 28

Welcome to the next edition of the Community Platform Update. This is a status …

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,113 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 229,918 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans