Hi,
I am using project management and accounting module with the projects as internal project type.
My business requirement is that when I would receive services then the cost should charge to the account code as per the project module.
Example - Project id is PRO1 and category is Audit fees. Posting profile for the same is 57001.
I have created service1 as the non stocked item in catalogue.
Now, the PO is created for the service1 with the above mentioned project id and category.
On product receipt the system is passing the below mentioned entry :- Purchase expenditure, uninvoiced A/c ....Dr
To Accrual A/c
On invoicing the following entries are passed :-
Accrual A/c ....Dr
To Purchase expenditure, uninvoiced A./c
Project cost A/c (57001)....Dr
To Vendor A/c
But the requirement is that system should post the mentioned entry at the time of product receipt - Project cost A/c ....Dr
To Accrual A/c
The objective is to record the cost in the expense account at the time of product receipt instead of invoicing. We are following monthly closing and are required to report monthly data to regulatory authorities.