MRP Working days conflict to Delivery Date sale lead time

(0) ShareShare
ReportReport
Posted on by 507

Hi guys,

We are new in MRP then we setup working days as Mon-Fri.However, we also want to let Sales admin have the option of selecting Delivery date on Sat and Sun (Sales is the most important department).

Unfortunately, we cannot satisfy requirements between 2 departments because this issue:

If Delivery date control: Sales lead time +1 working day:

- If sales create order on Sunday, the next delivery day is on Tuesday. This is not our expectation. We expect to delivery on Monday. Sales admin dont want to update manually. 

If delivery date control is sales lead time +1 (not working day):

If order is created on Friday, the next delivery on Sat (WH will not open on that day)

If order is created on Sat, the next delivery on Sun (WH will not open on that day)

Can you please advise what we should do?

We want to keep working days is Mon-Fri for MRP, also allow Sales to select Sat or Sun as delivery day and avoid these above issue.

Many thanks

Ett 

 

  • Community Member Profile Picture
    on at
    RE: MRP Working days conflict to Delivery Date sale lead time

    Hi ETT,

    Yeah, that's it.

    Also in the document there is a calendar called "Shipping calendar for a legal entity" that may work.

    If you are a developer, I suggest you go to read the code about calculating the delivery date of sales order,like class: SalesCalcAvailableDlvDates where you can find other settings that influence the delivery date calculation and may be used to achieve your goal or you can directly make customization to achieve it.

    regards,

  • Ett Profile Picture
    507 on at
    RE: MRP Working days conflict to Delivery Date sale lead time

    Hi Leo,

    In wonder if the calendar for WH. But I think It still affects to Master Planning

    pastedimage1618300546896v2.png

  • Community Member Profile Picture
    on at
    RE: MRP Working days conflict to Delivery Date sale lead time

    Hi ETT,

    I suggest using sales lead time +1 (not working day).

    Please refer to the document here:docs.microsoft.com/.../supply-chain-calendars-master-planning

    There is a calendar setting for warehouse that can be used to make the weekends unavailable.

    Please test it in the test environment before applying in live-environment.

    regards,

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Daivat Vartak – Community Spotlight

We are honored to recognize Daivat Vartak as our March 2025 Community…

Announcing Our 2025 Season 1 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Kudos to the February Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 293,245 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 231,923 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156 Moderator

Leaderboard

Product updates

Dynamics 365 release plans