Dear All
My client is a rice processer, we have production I & II here I am facing following problem:
We have two Sites opened in AX Site 1 and Site 2, each Site has Production Units. We have created Single BOM and Multiple Routes (Site wise) for Finished Goods. Order is received at Site 1 only it is a part of regular cycle that if order is huge in size then it is divided and processed on both sites.
Now in AX when I run Master scheduling AX schedules the order on the Site which is given on Sales Order and if the quantity is greater than daily capacity of work center then it schedule it in early dates so that delivery can be made on requested ship date.
How can I split the order and then schedule it to get processed simultaneously on both the sites?
Please help
Regards
Muhammad Saad