Hello Everyone,
I have a production order with 2 lines of routing operation. Operation 1 is a machine center and the run time of it is 2 hours. Now, I am changing the run time from 2 to 8 hours. But, simultaneously, the starting date is changed to 8 days previous to the current starting date. It is a backward scheduling so, I understand the start date is going backward. But, my question is, why it moved to 8 days backward. Because, the unit of measure for the runtime of the machine center is in Hours. So, if I change from 2 to 8 it should be scheduled on the same day or one day before. But, I am not understood why it went 8 days backward. Can anyone help me here to understand this concept?
Thanks,
Mani