I have long running production orders (multiple days) and MRP is pegging sales orders correctly at production order end date.
Though the products are becoming available almost on a daily basis and I want to know if it is possible to tell the MRP to
calculate the delivery date based on real availability out of production.
Let me make an example.
A planned production order for 1000 pieces is planned to start today and end in 10 days.
I have 10 sales order each for 100 pieces
MRP is pegging all the sales orders with a delivery date in 10 days from today.
Nevertheless production is 100 pieces per day, so sales order 1 can be served on day 1, sales order 2 can be server on day 2 etc etc
Is there a way to have MRP doing so?