Percentage Completed is always show 100% on estimates

(0) ShareShare
ReportReport
Posted on by 70

Hello All Expert,

I am new at Project management and accounting and started working on D365.
I am working on Fixed Price project type. First in Project Group on 

Revenue Recognition field : Completed Percentage 

Calculation Method : None

Matching Principle: Sales Value

After creating project I created one hour forecast line and after that created on on account transaction line.
Created one hour journal.
While estimates its showing 100% on the percentage completion and I am not getting the reason behind that. I tried 3-4 times.

In Hour Forecast I used 100 hrs, cost amount 20000, sales amount 30000
On account transaction Sales value 50000
Hour journal 20 hrs Cost amount 400
but still it is showing 100% in estimates. Please help me into that. I will be grateful, working on it from 3-4 days.
Thanks in Advance

  • MarkB45 Profile Picture
    755 on at
    RE: Percentage Completed is always show 100% on estimates

    Hi,

    As already stated make sure your cost template is correct but also ensure you are running the estimate agains the cost templates with the below settings and select the correct forecast model where you have the created the hour forecast line.

    pastedimage1665053315123v1.png

  • Suggested answer
    Manilal Profile Picture
    10 on at
    RE: Percentage Completed is always show 100% on estimates

    HI Team, 

    Just check your cost template is configured properly. If the estimation is based on Hour quantity the completion bases should be quantity as shown in below screenshot.

    3250.pastedimage1665043977109v1.png

    Regards

    Manilal

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at
    RE: Percentage Completed is always show 100% on estimates

    Hi,

    What forecast model did you select when you run the estimate?

    The one that includes your hour forecast or something else?

    Best regards,

    Ludwig

  • Suggested answer
    Veronika Filonenko Profile Picture
    1,255 on at
    RE: Percentage Completed is always show 100% on estimates

    Hi, 

    #1) 

    Are you doing manual progress billing or automatic? That has an impact, because you must then tell the system, in the billing rule, what are your chargeable categories? 

    #2) 

    Have you set up a contract value in the billing rule? That is mandatory for % calculation

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

November Spotlight Star - Khushbu Rajvi

Congratulations to a top community star!

Forum Structure Changes Coming on 11/8!

In our never-ending quest to help the Dynamics 365 Community members get answers faster …

Dynamics 365 Community Platform update – Oct 28

Welcome to the next edition of the Community Platform Update. This is a status …

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 293,110 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 231,886 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156 Moderator

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans