Skip to main content

Notifications

Announcements

No record found.

Community site session details

Community site session details

Session Id :
Microsoft Dynamics NAV (Archived)

Suggest me the process of material rejected by quality control and has to be sent back to the vendor either by stores or purchase dept.

(0) ShareShare
ReportReport
Posted on by 490

Suggest me the process of material rejected by quality control and has to be sent back to the vendor either by stores or purchase dept.

*This post is locked for comments

  • Verified answer
    Aleksandar Totovic Profile Picture
    Aleksandar Totovic 16,765 on at
    RE: Suggest me the process of material rejected by quality control and has to be sent back to the vendor either by stores or purchase dept.

    You can make Return Orders with quantites from "Scrap Location". If you use lots, you can find vendor of any scrap quantity, using Item Tracing.

  • srikanth k Profile Picture
    srikanth k 490 on at
    RE: Suggest me the process of material rejected by quality control and has to be sent back to the vendor either by stores or purchase dept.

    Thanks for the sugestion. As suggested by your good self, finally the rejected material get dumped in "Scrap Location". Is there any way to move the material away from scrap location through proper channel.

  • Suggested answer
    Aleksandar Totovic Profile Picture
    Aleksandar Totovic 16,765 on at
    RE: Suggest me the process of material rejected by quality control and has to be sent back to the vendor either by stores or purchase dept.

    This is complex process and need detalied analysis. Raw material by standrad comes to consumption based on BOM. You can change this on PO Components (you can insert, modify or delete row materials and planned material quantity consumption).

    You can always reject material on Consumption Journals or Production Journals. Quality Constol doesn't exist in standard NAV, but you san use "Quality Location". All planned material consumption you must transfer to this location before production. After controle is verifying you can transfer this quantity to "Production Location". All rejected material quantity you need transfer back to "Scrap Location".

    This is only sugestion, but this is no realy QM. There are few QM vertical solutions or you need to make serious anlysis and make some customization.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Daivat Vartak – Community Spotlight

We are honored to recognize Daivat Vartak as our March 2025 Community…

Announcing Our 2025 Season 1 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Kudos to the February Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 292,516 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 231,409 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans