Skip to main content

Notifications

Microsoft Dynamics GP forum
Unanswered

Outsourced MO WIP labor cost is not moving to FG after completing or closing the MO

Posted on by 606

Hi All,

We have outsourced MO's that are still having amount pending in WIP labor GL account even after closing the MO. We are moving those amount manually at the end of month.

But what could be the reason for this amount to remain in WIP labor even after closing the MO?? We also do partial receiving of MO and GRN's. Will this be a problem??

If receiving the GRN after completing the MO is cause of this?? If anybody can shed some light on this it would be much helpful. 

Thanks,
Arun.

Categories:
  • RE: Outsourced MO WIP labor cost is not moving to FG after completing or closing the MO

    Hello Arun,

    There would be no MO setup that would stop an outsourcing receipt from appearing in the MO Activity window for an MO. As I mentioned above, it was either not associated with the MO or the MO was closed prior to the outsourcing receipt posting. Another possiblity is that there were posting issues when you posted the outsourcing receipt. 

    Becky

  • Arunsh Profile Picture
    Arunsh 606 on at
    RE: Outsourced MO WIP labor cost is not moving to FG after completing or closing the MO

    Yes Becky I meant Outsourcing receipt entry in MO Activity. is there any way this could be stopped?? Is there any setting in MO setup to stop this?

  • RE: Outsourced MO WIP labor cost is not moving to FG after completing or closing the MO

    Hello Arun,

    I am not sure what you mean by "entry is not found in MO's". I am assuming you mean the Outsourcing receipt does not appear in the MO Activity window for this MO. If the outsourcing receipt does not appear in the MO Activity window, the outsouring PO was not linked to the MO or the outsourcing receipt was brought in after the MO was closed.

    Becky

  • Arunsh Profile Picture
    Arunsh 606 on at
    RE: Outsourced MO WIP labor cost is not moving to FG after completing or closing the MO

    Thank you Becky, but I would like to elaborate the partial receiving scenario so that I can give it to you correctly,

    MO Qty 10

    GRN partially received 5 Qty and MO partially completed for 5 Qty

    After some days, remaining 5 Qty is received through GRN and remaining MO qty 5 is completed.

    Will this impact the WIP labor? I have gone through multiple MO's to find this, only difference I could find is there is a line entry for Outsourcing in MO's which are correctly processed, and this entry is not found in MO's which are wrong.

    Is there any way to correct this wrong MO's? And is there a way to control this? This is becoming a nightmare when auditing.

    Thanks,

    Arun.

  • RE: Outsourced MO WIP labor cost is not moving to FG after completing or closing the MO

    Hello Arun,

    Yes, it could. If you are doing partial receipts and then complete the MO prior to receiving all items, there will be cost left in WIP for the oursourcing receipt. However, when you close the MO, these cost will be removed and placed in a variance account.

  • Arunsh Profile Picture
    Arunsh 606 on at
    RE: Outsourced MO WIP labor cost is not moving to FG after completing or closing the MO

    Thank you Becky. Yes we are using GRN a POP Receipt for Outsourcing PO. There are several MO's were receipt is received before MO is complete. Those MO's are not having any problem. But there are MO which are partially received, for those partially completed MO's GRN is also partially received. I am not sure how GP handles this partial receipt. Will this partial receiving impact ?

  • RE: Outsourced MO WIP labor cost is not moving to FG after completing or closing the MO

    Hello Arun,

    Thank you for using Community Forums. My name is Becky and I will assist you.

    Is a GRN, a pop receipt for the outsourcing PO?

    As long as the outsourcing PO was linked to an MO, there should be no cost left in you WIP labor GL account after the MO is closed.

    If you receive the outsourcing PO after the MO Receipt, the cost will not be applied to the finished good, and they will remain in WIP until the MO is closed.

    If you receive the outsourcing PO after the MO is closed, the cost will remain in WIP and not be removed.

    If you are receiving the outsourcing PO before you complete the MO receipt, the cost should go into the finished good, and be removed from WIP.

    If you are receiving the outsourcing PO prior to the MO close, I would suggest opening a support incident for a technician to take a look.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Dynamics 365 Community Update – Sep 16th

Welcome to the next edition of the Community Platform Update. This is a weekly…

Announcing Our 2024 Season 2 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Dynamics 365 Community Newsletter - September 2024

Check out the latest community news

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 290,522 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 228,441 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Product updates

Dynamics 365 release plans