Its a simple question as clear in Subject.
I have long production Orders, say One year. I had requirement of x number of jobs in route card at time of starting the Production order.
Now im in middle of Production, and i m not in need of some jobs or want to change some jobs.
How can i achieve this?
We cannot delete a job from Production route. Rather what we can do is:
Using Job updating function on All production orders>Production tab>All jobs>Job
We can remove the job and then update production route card to adjust the sequence of operations manually to exclude the operation no more needed with also adjusting time to 0, and then Reschedule.
Note that Rescheduling needs permission in Production Parameters> Statuses.
Let me know if anyone has faced that and found some better wayout.
Hi Ludwig
Thanks for response.
Please see below:
Installed product version : 10.0.18 (10.0.793.115)
Installed platform version : Update42 (7.0.5968.17070)
Hi Munbeen,
What AX/D365 version do you operate?