web
You’re offline. This is a read only version of the page.
close
Skip to main content

Notifications

Announcements

No record found.

Community site session details

Community site session details

Session Id :
Microsoft Dynamics AX (Archived)
Unanswered

On-hand is incorrectly pegging planned batch orders before production lines in master planning

(0) ShareShare
ReportReport
Posted on by

We are experiencing an issue where on-hand is incorrectly pegging future planned batch orders (formula lines) before pegging firmed production lines that lies more closer in time.

Coverage code is set to Requirement, where coverage time fence=365, positive days=365 days, negative days=365. Planned batch orders are firmed approximately 90 days before production start for an order but it can differ.

I have no safety stock (minimum) setup and the parameter is set to consume on-hand before all other inventory.

If I set positive days= 90 days the problem "disappear" since the planned batch orders starting 90 days from now will not be able to "reach" the on-hand  stock anymore. However, this solution is not good enough. I want the positive days to remain as long as the coverage time fence (to be able to use the on-hand stock full coverage time fence) but at the same time I want the on-hand stock to peg the production lines more close in time before pegging future planned batch orders.

Any ideas?

We are working in AX 2012 R3 CU11.

*This post is locked for comments

I have the same question (0)
  • gkumar Profile Picture
    740 on at

    Hi Icepennan,

    Can you try the below setting changes and confirm if  either of these wok for you:  

    1.In the Coverage group, can you check if consume on hand inventory is set to "Before all other supply".

    2.You have set negative days to 365,which in some sense also means  you can delay the customer order by these many number of days;ideally this number should be very small,can you change to say 5 or other smaller number and re -run the plan.

    Thanks,

    Ganesh

  • Weaveriski Profile Picture
    23,618 Moderator on at

    Could you post a picture of the net requirements so we can see the picture. As the demand is requirement how is the supply created for the actual production lines - what are the action/future messages if any on the actual production lines?

  • Community Member Profile Picture
    on at

    Hi Ganesh,

    Thank you for your answer!

    1) Coverage group is set to consume on hand "Before all other supply"

    2) I have tried to change the negative days multiple times. Unfortunately, it does not help me if I change the negative days to a smaller number. For e.g. I tried with negative days= 0 /2.

    Any other ideas?

  • guk1964 Profile Picture
    10,888 on at

    Are the earlier planned orders marked in any way to other orders?

  • Community Member Profile Picture
    on at

    Hi Steven,

     

    Picture 1 - Example of Net Requirement for item X. On-hand stock on warehouse 13 =6 pcs. We have several production lines (firmed batch orders) scheduled up until 18/6-2018 (se picture 2). However, as Picture 1 shows below - the on-hand stock is pegging towards future formula lines instead of pegging towards production lines that is scheduled more close in time.

    61764.Capture.PNG'

    Picture 2: Net Requirement for item X. Picture shows that we have production lines scheduled up until 18/6-2018.

     We do not use Action or future messages.

  • Community Member Profile Picture
    on at

    Picture 1 

    73768.Capture.PNG

    Picture 2 

    73768.Capture.PNG

  • Weaveriski Profile Picture
    23,618 Moderator on at

    Why is there no replenishment order on 08.03.2018 when the stock goes negative in picture 1? When was the static plan last run? You are selecting line 2 are warehouse 13 which has a planned order type of Transfer, so we should be seeing transfers from warehouse 2.  Are the planned orders for the held stock approved orders (so do not get re-generated?). Are you running full regen from the periodic option?

  • Community Member Profile Picture
    on at

    Hi Steven,

    Sorry, I was showing a print screen from a test system with old data. However, same situation in the Production environment where the data is up to date. Regeneration is run every day from the periodic option.

    As you can se in the picture below, planned transfers are suggested earlier than needed (since on hand is pegged against Formula lines instead of the firmed production lines) and we start to "build" on-hand inventory levels at warehouse 13 that we do not want.

    CaptureMRP2.PNG

    Please let me know if you have any ideas about what can be wrong.

  • Weaveriski Profile Picture
    23,618 Moderator on at

    Can you change the coverage group at 13 to RM50 and rerun a full regeneration? Does the picture change?

  • Community Member Profile Picture
    on at

    Almost the same picture here unfortunately. The difference is that we initially gets negative numbers for the on-hand stock at warehouse 13. This is because negative days on coverage group RM50= 400 which is equal to the lead time for the products.  However, as you can see the problem still appear with on-hand stock pegging future formula lines before production lines.

    CaptureMRP3.PNG

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans