I need create a single Purchase Order from multiple Purchase Requisitions lines

(0) ShareShare
ReportReport
Posted on by 76

In the 'Release approved purchase requisitions' form, I select multiple PR lines and click the 'Purchase order' button. I select the same provider for all lines, I click OK and it creates two separate POs. From what I could see is that the PRs have different applicants. Is there any way that I only get one PO?
Thanks in advance for your help.
We are using AX2012 R3 CU 10

I have the same question (0)
  • André Arnaud de Calavon Profile Picture
    301,069 Super User 2025 Season 2 on at

    Hi Maximiliano,

    Do you really mean 'applicants' or do the lines have different 'requestors'?

  • Maxi Martinez Profile Picture
    76 on at

    Hello Andre,

    I do mean requestors indeed, sorry for the mistake.

    Thanks in advance for your help

    Regards

  • Verified answer
    MATTGUO Profile Picture
    22,349 Moderator on at

    Hi,

    You need to use the consolidation feature, please check the Doc for details: docs.microsoft.com/.../key-tasks-consolidate-purchase-requisitions

  • Maxi Martinez Profile Picture
    76 on at

    Hello MATTGUO,

    Thank you very much for your help, make the configuration so that I do not divide the POs when I consolidate them, but even so, when the lines are PR with different requester, AX split them the same.

    pastedimage1605192518328v2.png

    Can you help me, please?

    Thank you

  • MATTGUO Profile Picture
    22,349 Moderator on at

    Hi,

    Are both PR lines the same except for the requester?

    Do you enable the demand consolidation in the purchase policy?

    If necessary, please share the steps you did.

  • Maxi Martinez Profile Picture
    76 on at

    Hello MATTGUO,

    reviewing more in depth when conducting more tests, we both realized that in reality the reason why it generates more than one PO is if the requisitors are from different areas, and that is not a problem for us,

    Thank you very much for your help and that of others,

    This issue is resolved

    Thanks a lot

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 592 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 478 Super User 2025 Season 2

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 305 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans