web
You’re offline. This is a read only version of the page.
close
Skip to main content

Notifications

Announcements

No record found.

Community site session details

Community site session details

Session Id :
Microsoft Dynamics AX (Archived)
Answered

Phantom BOMs only plan when explicitly called

(0) ShareShare
ReportReport
Posted on by 1,632

When running planning, the demand is only planning down to the Phantom and then stops.  So, I have to run a separate MRP run that explicitly calls out the items that are marked as phantom, then they continue to plan.  This is providing very bizarre results.  If I run planning for the item specifically (update master planning from net requirements), then the plan looks correct.  But if I run planning for everything, then I don't get the demand from the phantoms.

My question then, is there a setting on the item/BOM/parameters that controls how the phantoms are planned?  Does anyone else have this issue or have you seen an issue when using MRP with Phantoms?  From my research, most complaints are that Phantoms create planned orders, but in my case, I'm not getting these planned orders and I want them.

*This post is locked for comments

I have the same question (0)
  • FAC.Ansel Profile Picture
    1,632 on at

    To add to this....

    It appears that it is not a Phantom issue, as I have found that 1 Phantom will plan as desired but another one only shows the demand and does not generate supply.  If I run the planning run on this item, it creates the planned production orders but does not do this when run as a whole.  BOM Levels?

  • Guy Terry Profile Picture
    28,924 Moderator on at

    Are you expecting Master Planning to plan production orders for your phantom BOM lines?

  • FAC.Ansel Profile Picture
    1,632 on at

    Yes, I would expect to see Planned Production orders (dynamic) in net requirements to drive the material below the phantom. 

    Here is an example.  These are 2 different item numbers that should be planning the same way.

    The one on the left shows the demand but did not create any planned production orders.  The one on the right has both demand and planned production orders:

    MRPissues.jpg

  • Suggested answer
    FAC.Ansel Profile Picture
    1,632 on at

    After a lot of digging, research, testing, and retesting, I found the issue and solution.

    The problem was with the BOM Level on the items.  After running the BOM recalculation, I still calculated the same wrong levels and continued to have the same issues.  In a test environment, I manually updated the BOM level in the inventtable and ran scheduling and got the desired results.  It appears that the recalculation considers the Production BOM's which in this case had been used in a circulatory way.  So, I commented out the section of code in Class BOMLevelCalc/loadDependencies under "Get Data from ProdBOM". Then ran the recalculation.  This time the levels were correct and the master scheduling run exploded the BOM's as expected.

  • Douglas Noel Profile Picture
    3,905 on at

    Thank you for the post.

    Think this will help other a lot.

    Great.

    Douglas

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans