Hi all

Possibly post an update we have lost the "Work Hours" Tab / Calendar from the form.

I have removed the "Work Hours" from the form then re applied it and still does not appear.

It's a bit tricky as I presume it's some sort of box / iFrame and Work Hours is not an entity.

Last time I imported I believe that it's a hidden calendar entity.

All hours are still correctly showing on the Schedule board.

Have a support ticket open wondering if anyone else affected.

Thanks

Antony

  • antc Profile Picture
    2,909 on at
    RE: "Work Hours" missing from Resources Form

    This has now been resolved by MS and is working OOB.

  • Suggested answer
    Gabriel Dias Junckes Profile Picture
    2,428 on at
    RE: "Work Hours" missing from Resources Form

    Hi.

    The Work Hours is a PCF component. You have two options, add it back to the form via classic UI, or if you did not have much customization in your form, you could remove the Active Layer.

    pastedimage1622490517161v1.png

    Regards,

    Gabriel.

  • Verified answer
    Buli Ganguly Profile Picture
    on at
    RE: "Work Hours" missing from Resources Form

    Hi Antony,

    Please check if the entity Bookable Resource is using a custom form ‘Bookable Resource (UI)’, then this form could be missing the Work Hours tab. When switch back to the OOB form 'Information', Work Hours tab must appear as intended.

    Please be instructed to modify the ‘Bookable Resource (UI)’ form to meet the expectation.

    Modify the Bookable Resource (UI) form in the support instance 

    • Open the Bookable Resource (UI) form, insert a new tab, name it Work Hours.
    • In the tab Work Hours, drag and drop the field Calendar.
    • Double click on the field Calendar, go to Controls and add Work Hour control
    • OK > Save > Publish > Publish all customizations.

    After that Work Hours tab will be working on your Bookable Resource (UI) form. 

    In case, you are not using a custom form ‘Bookable Resource (UI), for next step, could you please do below steps:

    Login the Power Platform admin center by admin.powerplatform.microsoft.com.
    Login to your the environment
    Please check if there is any update available to the: Dynamics 365 Service Scheduling.

    If so, please update to the latest version.

    Thank you for using Microsoft Dynamics 365 Communities!
    Buli Ganguly
    Support Engineer for Dynamics 365 

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Daivat Vartak – Community Spotlight

We are honored to recognize Daivat Vartak as our March 2025 Community…

Announcing Our 2025 Season 1 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Kudos to the February Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 292,865 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 231,723 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156 Moderator

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans