Stock Write Downs

(0) ShareShare
ReportReport
Posted on by 397

Hi,

We have never done this yet, how do we update unit costs of our items for our stock write-down process? The accountants have updated the unit costs of a spread sheet so how can i now use this spread sheet to import and update into NAV? Is it via Revaluation Journals?

I tried to do a test on one item and changed the cost from 0.708 to 0.6 however when checking the item card it's 0.60033. Why would this be?

*This post is locked for comments

I have the same question (0)
  • Verified answer
    Suresh Kulla Profile Picture
    50,243 Super User 2025 Season 2 on at

    Which costing method are you using? If you are using standard please follow this link

    https://msdn.microsoft.com/en-us/library/hh168409(v=nav.90).aspx

  • CILGroup Profile Picture
    397 on at

    Sorry forgot to mention we use the Average Costing method on a item level.

  • Verified answer
    Alexander Ermakov Profile Picture
    28,096 on at

    You can indeed use Revaluation Journals for that. Check how "How Microsoft Dynamics NAV Calculates the Unit Cost on the Item Card": www.archerpoint.com/.../how-microsoft-dynamics-nav-calculates-unit-cost-item-card

    Have you run Adjust Cost – Item Entries batch job ? Please refer here: msdn.microsoft.com/.../hh169034(v=nav.90).aspx

  • CILGroup Profile Picture
    397 on at

    If we use average cost method and 'Automatic Cost Adjustment' is on, do we still need to run the batch job?

  • ManishS Profile Picture
    86 on at

    Yes you should do this before revaluing the cost.

  • Verified answer
    tpupko Profile Picture
    2,048 on at

    Hi,

    Steps:

    1. Run Adjust Cost - Item Entries

    msdn.microsoft.com/.../hh169387(v=nav.90).aspx

    2. Fill entries in Revaluation journal and post

    msdn.microsoft.com/.../hh168236(v=nav.90).aspx

    3. Run Adjust cost - Item Entries one more time

    Check what setting do you have in Item Ledger Setup for field Automatic Cost Adjustment?

    if Automatic Cost Adjustment = Always do only step 2 in other cases do 1-3 steps.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics NAV (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans