Is there a way to treat Indirect cost variance at the end of the Production order

(0) ShareShare
ReportReport
Posted on by 14,855

Dear 

I am applying indirect cost to my production order but usually some indirect cost such as overall electricity bill doesn't meet the expectation , is there a way for me to enter indirect cost price variance and recalculate it over the production orders ?

regards

*This post is locked for comments

I have the same question (0)
  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    HiI Silvano,

    You entered a surcharge in your costing sheet to cover indirect costs, is that right?

    What do you mean by enter indirect cost pice variance? Do you use standard costs and want to adjust/overwrite the cost price variance that AX calculates?

    Ludwig

  • Abdo Khoury Profile Picture
    14,855 on at

    Yes , exactly a surcharge that covers indirect cost that were not exactly calculated or properly foretasted prior to production

    well i am using the standard cost and the i am using the indirect cost as amount or % , but at the end of a certain period , we need to adjust the amount that we used as indirect cost over the production orders that we already produced ,

    is there a way to do that?

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Silviano,

    The surcharge is a king of 'allocation' that you specified.

    This allocation can be right or wrong; meaning that it will most probably differ from the actual costs that you experience and record.

    There is no standard way of allocating the total costs that you recorded subsequently to your production orders.

    In your General Ledger you will most probably have two accounts for that - one that tracks your actual costs and one that is used for posting the allocation in the costing sheet.

    You could then on a GL level do a kind of allocation by using a different sub-account to get your financial reports so to say 'right'.

    Yet, in the production area you cannot do that except by continuously tracking the over/underallocations that you have and adjusting the allocation % or rate that you specified in order to Keep the variance small.

    Hope that helps,

    Ludwig

  • Community Member Profile Picture
    on at

    Hello Silvano

    Try use Adjustment transaction from Closing and adjustment. If you find there only transaction with reference production (from last month) and adjustment it by amount ....    May be this is a way to solve this business  case.
    I know it is not perfectly solution by sometimes used by clients

    Best regards

  • Suggested answer
    Fredrik Sætre Profile Picture
    12,644 on at

    Is it just power or other costs like rent and such?

    I can give you a pointer on the power consumption.

    You probably in this case have some type of variable power consumption that you would like to add to your item cost. Right? The way to do this is simply adding this as a direct manufacturing cost as you can actually measure this quite effectively.

    If you purchase your power in kWh as a service item (you need to have the "non stocked" box unchecked to be able to add it a BOM).

    Then add it to your BOM as an estimated cost of x kWh and correct this by entering the right consumption like picking an item. Your cost for each kWh will be based of the purchase price. Maybe weighted average costing method is preferred.

    If it is a bunch of indirect manufacturing costs, you would add these through the costing sheets as a percentage based of of one of your consumed resources. Normally we add an additional cost to the resource for things like power, rent and maintenance and for the item calculate the cost for each item for covering handling and warehouse costs.

    Check out costing sheets for more info.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#1
Priya_K Profile Picture

Priya_K 4

#3
MyDynamicsNAV Profile Picture

MyDynamicsNAV 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans