Skip to main content

Notifications

Announcements

No record found.

Microsoft Dynamics AX forum
Suggested answer

Selecting alternate resource with it's Relative capacity

Posted on by 2,692

I have two machines M1 and M2. M1 produces 1000 Pcs of Item A in an hour time and M2 Produces 500 Pcs of Item AX in hour time.

I want system to schedule production order first on M1 (estimated time of completion is 1 hour for 1000 Pcs) and if capacity is not available on M1, system can pick up M2 (estimated time of completion is 2 hours in this case).

How can I setup this situation?

I already explored the concept of capability and limitation with capability is that resources with same manufacturing capacity (against particular product) can only be assigned to same capability. In my opinion Capability should refer to particular capability a resource can perform without getting bothered about it's capacity. System once identifies the resource, should pick up the relative capacity (from operation relation) if defined.

Another drawback of having operation relation is that, user cannot specify different capacity for different machines (but for the same product) using the same operation relation.

Ideally user should be able to specify information about "how much time it will take if Item A is produced on Machine M1 and how much time it will take if same item is produced on Machine M2" on the same operation relation.

  • HenkeNord Profile Picture
    HenkeNord 459 on at
    RE: Selecting alternate resource with it's Relative capacity

    Perhaps this thread is dead, but I'll try.

    Why is it so "hard" for AX to select the alternative resource if I have a capability with two resources.
    Even though the resource with highest priority is full and my sales orders cannot be delivered on time, the free alternative resource isn't selected.

  • Weaveriski Profile Picture
    Weaveriski 23,616 on at
    RE: Selecting alternate resource with it's Relative capacity

    If you want to schedule production on an alternate resource you can update the route manually and reschedule or at creation pick the alternate route.

    Capability is an overlay to capacity to match requirements, the capacity is separate but obviously if the item has a set capability it needs to schedule and then calculate based upon the capacity.

  • Rahul Shah Profile Picture
    Rahul Shah 2,692 on at
    RE: Selecting alternate resource with it's Relative capacity

    Ok, it means capability can only be used to group resources having same capacity for particular item. Right? And if we want to schedule production on alternate resource than resource need to be changed manually on production route. Right?

  • Weaveriski Profile Picture
    Weaveriski 23,616 on at
    RE: Selecting alternate resource with it's Relative capacity

    Yes, it would be natural to have multiple routes in a multi-route/resource environment.

  • Rahul Shah Profile Picture
    Rahul Shah 2,692 on at
    RE: Selecting alternate resource with it's Relative capacity

    Does that mean, I need to maintain two routes for Item B, one for M1 and another for M2 with their relevant factor?

  • Weaveriski Profile Picture
    Weaveriski 23,616 on at
    RE: Selecting alternate resource with it's Relative capacity

    The way AX works is M1 has a capacity of "standard" flow irrelevant to the item, meaning you can take your Item A as your standard having 1000 M / Hour as an example meaning your factor is 1 on Item A's routing, and then your Item B factor would be 0.6 for the M1 machine. You establish a base and flex it per item with the factor.

  • Rahul Shah Profile Picture
    Rahul Shah 2,692 on at
    RE: Selecting alternate resource with it's Relative capacity

    I am also wondering if I can use 'Batch' and 'Resource Batch' capacity formula but I think these are relevant for batch orders though I could not find much details on this.

  • Rahul Shah Profile Picture
    Rahul Shah 2,692 on at
    RE: Selecting alternate resource with it's Relative capacity

    Hi Weaveriski,

    Few points:

    - I am maintaining route per product but not per resource (machine) instead i am using capability which will pick up the resource for scheduling based on priority

    - I can set the factor on route but same factor will not be applicable to both the machines for the same product

    I.e. Item A1, Factor 0.5, Capability = Packaging, Priority = 1, level =1, Run time = 1 hour, will pick up the machine M1 (having 1000 M / Hour) capacity defined on it, that means  M1 will take half an hour to produce 1000 M of item A1 which is correct and if system picks up the Machine M2 which has a capacity of 2000 M / Hour defined on it and will take 15 minutes of time to produce 1000 M of item A1

    - So far so good

    - Now let's talk about item B for which M1 and M2 has different capacity ( 600 M/ Hour and 800 M/Hour respectively) and I cannot setup the factor which gets me the appropriate run time for item B since resource capacity is already defined as 1000 M and 2000 M for M1 and M2

  • Suggested answer
    Weaveriski Profile Picture
    Weaveriski 23,616 on at
    RE: Selecting alternate resource with it's Relative capacity

    You can set the factor by route for each product, thereby flexing the capacity of the resource by product.

  • Rahul Shah Profile Picture
    Rahul Shah 2,692 on at
    RE: Selecting alternate resource with it's Relative capacity

    Hi George,

    I really appreciate your response. It is quite helpful.

    I understand that if resource capacity is based on formula, with the help of factor (as specified on route) system can calculate the run time accordingly based on the operation scheduled on particular resource.

    Question here is, what if factor varies from product to product for the same set of machines?

    I.e. Machine M1 has Capacity of 1000 M / Hour and M2 has 500 M/Hour for Product A and for

      Product B M1 has 300 M/ Hour and M2 has 700 M / hour.

    We can only specify one capacity i.e. 1000 M /Hour or 300 M/ Hour for Machine M1 but each product has different capacity and where to specify it?

    I hope I am able to explain my concern.

    Any idea how can we deal with this situation?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Anton Venter – Community Spotlight

Kudos to our October Community Star of the month!

Announcing Our 2024 Season 2 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Dynamics 365 Community Newsletter - September 2024

Check out the latest community news

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 290,554 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 228,588 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans