Hi all,

I'm testing out the new power bi embedded stuff in D 365 Finance. I have setup the power bi integration/configuration, D 365 is able to see my workspace.

Screenshot-2020_2D00_07_2D00_29-at-14.58.43.png

However if I try to insert my new modified version I get the below error. What else do I need to do to get this to work? Add a power bi gateway? If that is the case how come I haven't seen this is any of the D 365 documentation... thanks.

Screenshot-2020_2D00_07_2D00_29-at-14.51.22.png

I have the same question (0)
  • Suggested answer
    saurabh bharti Profile Picture
    15,039 Moderator on at

    Did you use power BI desk top / power Bi portal to design the same ? Did you used standard entity store or custom entity store?

    You can navigate to power BI desktop/portal and there check the data set settings .

  • WillWU Profile Picture
    22,361 on at
  • jhowe Profile Picture
    1,205 on at

    Hi Saurabh, thanks for your reply, i simply downloaded the practice manager pbix from LCS, opened in power bi desktop, stuck a logo on it and tried to pin it in my analytics tab and got the error you see above. Can you please explain or send link for the additional setup i need? I'm trying to do this on our UAT sandbox environment not 1box dev environment. Thanks! WillWU this looks useful for setup on the 1box dev environments... 

  • WillWU Profile Picture
    22,361 on at

    Hi jhowe,

    Embedded PowerBI requires F&O development/code deployment, and you have to have pbix files in deployment package.

    Please check:ajit-newdynamicsax.blogspot.com/.../power-bi-how-to-embed-pbix-in-d365fo.html

  • jhowe Profile Picture
    1,205 on at

    But I have simply modified an EXISTING out of the box report, and tried to stick it back into an EXISTING workspace?  I'm not trying to create a new one... this is where I'm getting confused... I understand the process for creating a new workspace.  

  • WillWU Profile Picture
    22,361 on at

    Hi jhowe,

    Yes, you have to add your pbix file to the workspace in DEV environment.

    docs.microsoft.com/.../add-analytics-tab-workspaces

  • Suggested answer
    jhowe Profile Picture
    1,205 on at

    Ok so found the correct process -> create app registration as per docs.microsoft.com/.../configure-power-bi-integration

    -> LCS integration needs to be setup in system administration -> system parameters

    -> PBIX file needs to be added to your LCS asset library

    -> Deploy power bi files needs to be done in system administration -> Deploy Power BI.  You can then add it to workspaces.

  • WillWU Profile Picture
    22,361 on at

    Hi jhowe,

    So you are talking about integration with PowerBi.com.

    The doc is about integration with PowerBi.com, not embedded PowerBI,reports deployed to PowerBI.com don't touch AxDW.

    Embedded reports use AxDW which is constructed form the entity store and refreshed from the entity store.

  • jhowe Profile Picture
    1,205 on at

    Hi Will,

    Ok I see I maybe confusing the two, I thought setting up the power bi integration was essential for power bi embedded, but I guess not. Therefore what is the point of the power bi integration as you cannot access AxDB through power bi correct me if i'm wrong?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 503 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 434 Super User 2025 Season 2

#3
BillurSamdancioglu Profile Picture

BillurSamdancioglu 278 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans