This forum is the last hope for me guys - Please Help - I am struggling a lot ! This has halted my project.
I have an already existing purchase order with a due date of 3/29/2024 .
System is suggestion an MRP PO [ MPO] with due date of 03/28/2024 & Release by date of 11/10/2023 [ Back in Time].
Purchasing lead time is 99 days & Planning time fence is 60 days.
Why system is not suggesting to 'MOVE IN' an already existing purchase order rather than suggesting a new purchase order & then asking it to bring on a day that is not feasible?
is that because of planning time fence? Can someone please help on it?
Ready to provide few more details as needed.
#MRP #Manufacturing #GP2018