I would like to Put my Question in Layman's term:
Our Organization is Using Dynamics Project Operations - lite module for a Civil Construction Company.
System Admin has created Project Templates for
Bathroom Built, Kitchen Built, Bedroom Built etc.
Bathroom Built Project templates has below Resource roles added - Which dictate's how many Human efforts will be required to acomplish construction of 1 Bathroom
5 hours for Role A i.e. Interior Designer
30 hours for Role B i.e. Tile Fitter
32 hours for Role C i.e. Laborer
44 hours for Role D i.e. Plumber
10 hours for Role E i.e. Carpenter
and in similar patter for respective Kitchen built, Bedroom built etc.
Company would like to create a Project / worked based Quotation for Multiple Flats (i.e. single unit of a 3 BHK Flat contains 3 Bathrooms) and there will be 44 Flats in 1 building.
So, Users are facing a toughtime generating a Quote for such building where logically total 132 Bathroom built.
When they select a Project Template and Copy the Project and Import Hours/estimates in Quote line details from Project; System Only fetches the Resource Role Break up as mentioned in above fashion.
Where the need all Quantity fetched by system at Quote line details level from Project needs to be multiplied with a definite variable number (i.e. 132 in above example.)
Only OOB way We found is literally Users needs to go in all Quote line details and Manually multiply the Quantity (132 * 44 for Plumber line) which is very teadious and can incur a lot of human errors.
It would be great help if anyone from community can provide a User Freindly solution to this problem.