I wud like to know the procedure for below.
e.g. For FG part no "A" there is one Sales Order no 1
Pls note FG part no A -bom is as below
SFG 1
SFG2
For SFG 1 manufacturing lead time is different i.e. lesser e.g. 7 days
For SFG 2 mfg.lead time is higher e.g. 15 days.
Mfg policy is make to order for FG 1.
As per std. if we release production order system releases both the SFG as per routing defined at same time.
This creates excess stock well in advance for SFG 1 which I would like to avoid.
How we should handle this ? i.e. SFG1 will be releasing after 7 days so as to avoid excessive inventory in WIP.
My purpose is to release two SFG at two diff.times since mfg lead time is different.
Thanx in advance
Regards
Prashant
*This post is locked for comments
I have the same question (0)If you have defined proper Lead Time and Routing for SFG1 & SFG2, system would automatically suggest the accurate start time for the both the production order in Planning Worksheet (backward scheduling).
i.e. SFG1 production order will start just before 7 days (production order due date), where as SFG2 will start before 15 days.
Can you let us know, where exactly are you facing the issue?