Hi,
We have Dynamics AX 2012 R3 CU 9 and we are using project budgeting with allow overruns.
If we have a project with categories A, B, C and D (Valid and Assigned) then we created an original budget for categories A and B only we can post post transactions using categories A, B, C and D.
According to our business needs, this scenario is Ok to avoid obstructing the daily business process and that is why we are allowing budget overruns.
But once creating a budget revision and adding category C (which is not listed into the original budget), we are not able to post on C category if the revision status is (Created / Submitted) and we are getting an error message 'Budget has not been adjusted correctly'
On the other hand, if we tried to post using category D which is not listed into any budget it is posting normally with no error.
Is it logic !! Where it is affecting our daily business process and we would like to understand the concept of this scenario if it is the default scenario and there is no bug.
Please advise