We only use currently operation schedule for the production work orders.
we use “Current Operations” ? Production control > Common > Current operations.
I was looking to see if I could find a way to view the schedule for a machine (resource) without using the gantt charts. as we don't have job schedule. I have used current operations before and thought this might be a good option as it breaks down the production orders into operations giving start and end dates. I looked at Production order which was the order we tested it gives me 36 lines of the run operation (op10)resource ,and for the sub operation (op20)1 time (resource group). I do not understand the 36 lines for the run operation ? why does it show it so many times ?
We only want to see the machine schedule for the week or month, what is the best way for that?
*This post is locked for comments
Could you provide a screen shot of the production route and the current operations screen - I am confused by your statement of 36 lines appearing when you have two operations.
Hi Ray,
For this I navigate to Organisation Administration > Common > Resources > Resources.
From here I can select the resource I want to see schedule for, then click Capacity Reservations from the 'view tab' within the header.
This gives an overview of operations the resource is/has been scheduled to perform, and you can filter the dates in which you want to view reservations
Hope this helps
Stay up to date on forum activity by subscribing. You can also customize your in-app and email Notification settings across all subscriptions.
André Arnaud de Cal... 291,134 Super User 2024 Season 2
Martin Dráb 229,928 Most Valuable Professional
nmaenpaa 101,156