While using Min-Max coverage group of an Item any way to group Planned orders for a period

(0) ShareShare
ReportReport
Posted on by 4
Hi,
 
I have a scenario-> Item is mapped with Min-Max Item coverage and coverage time fence days is 30 and positive days is 30.
We have a demand forecast lines defined for two diferent days 4th and 10th , 10000 and 25000 respective quantity
 
This item is a production item, so when we run MRP system generating three different planned orders, 
1- Based on Min-Max quantity
2&3 based on required quantity
But is there a way when system generating planned orders it should create only one.
 
Any suggestion please.
 
Thanks
Ram
I have the same question (0)
  • Suggested answer
    Kevin Xia Profile Picture
    Microsoft Employee on at
    Hi,
    Can you provide more information (such as system Settings or detailed screenshots, etc.) to help us better solve the problem for you? The information you have provided so far is not enough to support us to propose a solution. Can you provide ä»–å’Œscreenshot of the three planned orders for our reference?
    Best regards,
    Kevin
  • Suggested answer
    ColbyGallagher Profile Picture
    3,666 on at
    Change your item's coverage group to something that has a coverage code of "Period" and set your coverage period to 30 days, you'll get one planned order for all the requirements in the next 30 days: minimum inventory, demand on day 4 and day 10.  

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 611 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 529 Super User 2025 Season 2

#3
Sohaib Cheema Profile Picture

Sohaib Cheema 285 User Group Leader

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans