Posted on by 5

I have over 30 production orders released were we require a single part change over all the BOMS. They have the same routing No. so they're exactly the same BOM.

Is there a way to change all of the parts in 1 sweep or is it a manual task at this point?


Thanks

Categories:
  • Suggested answer
    Amit_Sharma Profile Picture
    Amit_Sharma 2,545 on at
    RE: Change the same part over several released production orders

    Hi,

    There is no such feature is in standard system. Create new batch job and in that batch job call the Refresh Production order no.. In that way you can achieve the requirement.

    Regards

    Amit Sharma

    www.erpconsultors.com

  • Suggested answer
    ew98000 Profile Picture
    ew98000 225 on at
    RE: Change the same part over several released production orders

    There is no batch type method to handle this that I know of. Once you have changed the BOM, you have 2 options that I can think of.

    1) Run the refresh on every production order - this will pick up the updated BOM. For 30 orders it's a bit of a pain but not a big deal really.

    2) Manually make the change on every production order component line - this is more tedious than 1st method and subject to error

Helpful resources

Quick Links

What Motivates a Super User?

We know many of you visit the Dynamics 365 Community and Power Platform…

Demystifying Copilot with Sundar…

Industry experts answer burning questions directly from our amazing Community…

Enabling Copilot Case and Conversation…

Agents can easily recap an ongoing chat, transcribe a voice conversation…

Leaderboard

#1
Andre Arnaud de Calavon Profile Picture

Andre Arnaud de Cal... 282,978 Super User

#2
Martin Dráb Profile Picture

Martin Dráb 222,562 Super User

#3
nmaenpaa Profile Picture

nmaenpaa 101,138

Product updates

Dynamics 365 release plans