I am using demo version of CRM 'project operations'.
'Tasks' have been configured in the project, and relationships are established only through 'Start to Finish' or 'Finish to Start'.
I should also use 'Start to Start' or 'Finish to Finish'.
I forced the 'Start to Finish' or 'Finish to Finish' option in the 'Project Task Dependency' Entity, but it did not apply to my P.O chart.
So, while searching with related keywords, I found and tried several methods.
In my opinion, the old "project.microsoft.com" is outdated and has now been integrated and absorbed into CRM. Do I understand this correctly?
Q. The document also had several limitations. Is it true that extension tools are not available in the trial version?
Q. Is it true that the information provided in the document I found will help me use additional functions from P.O to SS and FF options??
Please tell me how to freely form relationships between Tasks in 'd365 project operations' :(
I share my P.O screen.