We have problems that the first operation in our routes, material picking, starts many days before the second operation, when running master planning (job scheduling mode). This makes the material being piled next to our machines for days which isn't desirable. The material is linked to the first operation (end). The problem occurs when the resource in the second operation is full. I have tried with different settings on Link type (Soft, Hard and Blank) with no difference.
Example of jobs after running master plan, as you can see the first operation - material picking start 23/9, and the second start 15 days later, which isn't ok.

First operation resource workload

Second operation resource workload